Skip to main content

Nottingham City Council

  • Date 15 March 2011
  • Sector Local government
  • Decision(s) FOI 1: Upheld
The complainant requested, under the Freedom of Information Act 2000, information about documents that he had already received. The public authority responded and provided the information that it held. This response was provided late. There were two further exchanges of correspondence about matters of concern and the complainant complained to the Commissioner. During the course of the investigation, the complainant agreed that his complaint was focused on the delays that he had experienced. The Commissioner finds that the public authority has breached section 10(1). The public authority has provided the information to which the complainant was entitled and therefore the Commissioner does not require remedial steps to be taken in this case.