  • Date 9 August 2019
  • Sector Local government
  • Decision(s) EIR 5.1: Not upheld, EIR 5.2: Upheld

The complainant has requested quarterly information concerning Manchester City Council’s progress in meeting its Climate Change Action Plan.  The Council responded, providing some information falling within the scope of the request but advising information was not collated on a quarterly basis and would be available in the Annual Progress Report to be published in July 2019.  Following an investigation, the Commissioner’s decision is that Manchester City Council has provided all the information it holds falling within the scope of the request.  However, it failed to do so within the 20 working day time for compliance and therefore the Council has breached regulation 5(2) of the EIR.