Canal and River Trust
- Date 7 April 2020
- Sector Education
- Decision(s) EIR 5: Upheld
The complainant requested information about damage to the Toddbrook Reservoir spillway from the Canal & River Trust (‘CRT’). He submitted a complaint to the Commissioner as he had not received a response to this request. The Commissioner’s decision is as follows: CRT breached regulation 5(2) of the EIR as it did not provide the complainant with a response to his request within 20 working days. CRT has now provided a response to the request and, as such, the Commissioner does not require CRT to take any remedial steps.