Skip to main content

EDF Energy Limited

  • Date 5 September 2024
  • Authority EDF Energy Limited
  • Decision(s) EIR 2.2: Not upheld

The complainant has requested information about electricity standing charges. EDF Energy Ltd refused to comply with the request as it did not consider the information to be environmental or that it was subject to the EIR. The Commissioner’s decision is that EDF is not a public authority for the purposes of the EIR and therefore it was not under an obligation to respond to the request. As EDF is not a public authority, the Commissioner is unable to compel it to take any steps.